Construction Progress

Building Isuwa Khola

Monthly progress on every part of the Isuwa Khola Hydropower Project, from the overall completion figure to the latest notes from each structure on site.

Overall Status

Progress at a Glance

As of June 2026

71%Overall Project Progress
Download Progress Report
  • In progress

    Overall Civil Works

    74%
  • In progress

    Hydro-Mechanical Works

    65%
  • Complete

    Access Road

    100%
  • In progress

    Electro-Mechanical Works

    65%
  • In progress

    Transmission Line Works

    20%

Civil Works by Structure

  • Raised Weir and Intake69%
  • Desander7%
  • Headrace Pipe65%
  • Surge Tank60%
  • Penstock Pipe Alignment49%
  • Powerhouse90%
  • Tailrace100%
  • Switchyard60%
  • Protection Works Along Alignment90%

Site Updates

Structure by Structure

Latest construction notes from each part of the scheme, from the headworks high on the river to the tailrace below the powerhouse.

Headworks — construction progress
01 / 09

Headworks

The project continues to progress steadily across all major components at the headworks. Elevation gains at the raised weir, completion of foundational elements at the undersluice, and ongoing earthworks in the pondage area point to a positive trend toward key milestones. Current efforts are focused on increasing structure heights, backfilling, and implementing the proposed structural works at the pondage slope.

Raised Weir and Intake — construction progress
02 / 09In progress

Raised Weir and Intake

During the reporting period, significant progress was recorded at the raised weir, which now stands at an elevation of 1,997 meters — an advancement of 29 meters from the base. Work continues steadily alongside the undersluice and pondage area, keeping the intake structure aligned with the project's construction milestones.

Progress69%
Undersluice — construction progress
03 / 09

Undersluice

Concreting of the raft at the undersluice is complete. Vertical and radial gate embedments are installed, and both the left and right walls — 4 meters and 3 meters respectively from the bucket portion — are finished. The wall has been raised to the foundation level of the intake, and the intake's raft foundation is also complete.

Pondage Area — construction progress
04 / 09

Pondage Area

Slope cutting and heavy excavation are ongoing along the right bank upstream of the raised weir, spanning approximately 250 meters in length at a slope of 2:1, as the pondage structure is prepared for the project's peaking operation.

Headrace Pipe — construction progress
05 / 09In progress

Headrace Pipe

The headrace pipe alignment is accessible via a motorable road, supporting transport and construction activity. Excavation at crossing points is underway and blasting is complete. A total of 43 anchor blocks are finished, jacketing is progressing on most support piers, and 4,600 meters of pipe have been laid along the alignment to date. Four major siphon and bridge crossings are identified, with abutment construction in progress.

Progress65%
Surge Tank — construction progress
06 / 09In progress

Surge Tank

Concreting up to 6 meters from the crank level (EL. 1990.6) is complete, with backfilling around the surge tank also finished. Further concreting is temporarily on hold, with plans to use scaffolding relocated from the powerhouse.

Progress60%
Penstock Pipe — construction progress
07 / 09In progress

Penstock Pipe

Excavation from Anchor Block 17 to 18 through the concrete casing area upstream of the powerhouse is complete, with a saddle pad installed to support the pipe. Erection of 450 meters of penstock pipe and concrete casing of 220 meters are finished, with bioengineering planned to stabilize soil on the inclined section.

Progress49%
Powerhouse — construction progress
08 / 09In progress

Powerhouse

Civil works at the powerhouse are complete up to the corbel beam level, with rebar finished and formwork placed for concreting. Machine floor concreting is partially held back to allow the electromechanical contractor to install embedded parts for the turbine and generator. The cooling chamber is complete and the oil tank slab is underway.

Progress90%
Tailrace — construction progress
09 / 09Complete

Tailrace

The 82-meter tailrace has been completed in full.

Progress100%