


Investing in hydropower means reduced energy bills and long-term sustainability for communities and industries alike.

We are dedicated to pioneering the future of clean energy. As a leader in the hydropower industry, we leverage innovative engineering and sustainable practices to develop and operate projects that provide reliable, renewable power and drive national progress.
Civil Engineer
Installed Capacity
Annual Energy Output
Tons of CO₂ Avoided Annually
Local Jobs Created

The project continues to progress steadily across all major components at the headworks. Elevation gains at the raised weir, completion of foundational elements at the undersluice, and ongoing earthworks in the pondage area point to a positive trend toward key milestones. Current efforts are focused on increasing structure heights, backfilling, and implementing the proposed structural works at the pondage slope.


During the reporting period, significant progress was recorded at the raised weir, which now stands at an elevation of 1,997 meters — an advancement of 29 meters from the base. Work continues steadily alongside the undersluice and pondage area, keeping the intake structure aligned with the project's construction milestones.


Concreting of the raft at the undersluice is complete. Vertical and radial gate embedments are installed, and both the left and right walls — 4 meters and 3 meters respectively from the bucket portion — are finished. The wall has been raised to the foundation level of the intake, and the intake's raft foundation is also complete.


Slope cutting and heavy excavation are ongoing along the right bank upstream of the raised weir, spanning approximately 250 meters in length at a slope of 2:1, as the pondage structure is prepared for the project's peaking operation.


The headrace pipe alignment is accessible via a motorable road, supporting transport and construction activity. Excavation at crossing points is underway and blasting is complete. A total of 43 anchor blocks are finished, jacketing is progressing on most support piers, and 4,600 meters of pipe have been laid along the alignment to date. Four major siphon and bridge crossings are identified, with abutment construction in progress.

Concreting up to 6 meters from the crank level (EL. 1990.6) is complete, with backfilling around the surge tank also finished. Further concreting is temporarily on hold, with plans to use scaffolding relocated from the powerhouse.


Excavation from Anchor Block 17 to 18 through the concrete casing area upstream of the powerhouse is complete, with a saddle pad installed to support the pipe. Erection of 450 meters of penstock pipe and concrete casing of 220 meters are finished, with bioengineering planned to stabilize soil on the inclined section.

Civil works at the powerhouse are complete up to the corbel beam level, with rebar finished and formwork placed for concreting. Machine floor concreting is partially held back to allow the electromechanical contractor to install embedded parts for the turbine and generator. The cooling chamber is complete and the oil tank slab is underway.

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River scheme designed to deliver 674.30 GWh of clean, renewable energy annually to Nepal's national grid, supporting the nation's sustainable development goals.

We actively engage with and support local communities through various social initiatives, including road construction, gabion works, and assistance for essential services like drinking water and community facilities, ensuring shared growth and prosperity.

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River (PRoR) scheme, set to deliver 674.30 GWh of clean, sustainable energy annually to the national grid.
Our project features state-of-the-art infrastructure including a 6.9 km headrace pipe and a powerhouse with a gross head of 940m, reflecting robust design and construction progress. Overall civil works have reached 74% completion as of June 2026, with hydro-mechanical and electro-mechanical works both at 65%.

Beyond power generation, we actively support local communities through initiatives like road construction, gabion works, and essential material assistance for drinking water and community facilities.
Chairman
Director
Chief Executive Officer
Admin & Finance Officer
Civil Engineer
Civil Engineer
Procurement Officer

Power Purchase Agreement (PPA)

Marking a critical step towards project funding.

Chongqing Water and Turbine Work Co. Pvt. Ltd. (CWTW), China.

Original Commercial Operation Date (COD) as per PPA.(2024)

June 2025: Overall construction progress reaches 65%.

June 2026: Overall civil works progress reaches 74%, with hydro-mechanical and electro-mechanical works both at 65% and access road fully complete.

February 13, 2027 (Proposed): Revised Commercial Operation Date

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River (PRoR) scheme located in the Makalu Rural Municipality of Sankhuwasabha District, Koshi Zone, Eastern Region of Nepal. It is designed to contribute significantly to Nepal's national electricity network.
The project has an installed capacity of 97.2 MW.
The project aims to supply 674.30 GWh of annual energy to the Nepal electricity network.
As of June 2026, overall civil works progress stands at 74%, with hydro-mechanical and electro-mechanical works each at 65%, transmission line works at 20%, and the access road fully complete.
The Proposed Extended Commercial Operation Date (RCOD) for the project is February 13, 2027. The original Commercial Operation Date (COD) as per the Power Purchase Agreement (PPA) was October 13, 2024.
Key civil works include a raised weir (50m x 37m), a side intake with two orifices, a 6911.53m long headrace pipe, a circular surge tank, a 2500m long penstock, and a surface powerhouse (115m x 20m).
The project undertakes various social and community support works, including road excavation (e.g., Thange-Bhanjyang School road), gabion works for protection, financial assistance for community structures (e.g., Yangluwa Gangdhok Gumba), and material assistance for drinking water supply at Jimmy Village.
"The Isuwa Khola Hydropower Project has brought significant improvements to our daily lives, particularly with the road development and access to essential services. It's more than just a power project; it's a partner in our community's growth."

Share holder
"The Isuwa Khola Hydropower Project has brought tangible benefits to our village. The new access roads have significantly improved connectivity, and their support for our local Gumba and drinking water schemes shows a true commitment to community well-being. This project is making a real difference in our lives."

Community Leader, Makalu Rural Municipality
"As a partner involved in the civil works, I've been consistently impressed by the scale and precision of the Isuwa Khola Hydropower Project. The progress on critical structures like the powerhouse and headrace pipe is remarkable, reflecting strong engineering and dedicated execution. It's a privilege to contribute to such a vital national asset."

Construction Manager, Civil Works Contractor
"Our collaboration with K.B.N.R Isuwa Power Limited on the transmission line has been a testament to effective partnership. The project's strategic importance for Nepal's energy future is clear, and we're proud to be part of an initiative that is so crucial for national development and energy independence."

Project Coordinator, Transmission Line Partner

We're here to answer any questions you may have about the Isuwa Khola Hydropower Project. Feel free to reach out through the contact form below or use our direct contact information.
