The Project · Sankhuwasabha, Nepal

Isuwa Khola Hydropower Project

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River (PRoR) scheme, set to deliver 674.30 GWh of clean, sustainable energy annually to the national grid.

Installed Capacity
97.2 MW (3 × 34.1 MW)
Gross / Net Head
940 m / 914 m
Dry / Wet Energy
262.54 GWh / 411.76 GWh
Catchment Area
152 km²

How It Works

From River to National Grid

Water is diverted at the raised weir, carried 6.9 km along the hillside, then dropped 940 metres through the penstock to spin three turbines before returning to the river.

How the Isuwa Khola Hydropower Project works Profile of the scheme: the raised weir diverts the river into a headrace pipe that runs along the hillside to a surge tank. From there the penstock drops steeply to the powerhouse, the tailrace returns the water to the river, and a transmission line carries the power to the grid. 940 m gross head 1 2 3 4 5 6 7

Swipe to see the whole scheme

  1. 1

    Raised Weir & Intake

    50 m × 37 m weir · crest at 2,005 m

    Raises the river and diverts up to 12.6 m³/s through a side intake with two 2.5 m orifices. The pondage behind it stores water for peak-hour generation.

    Construction69%
    Latest update
  2. 2

    Headrace Pipe

    6,911.53 m · Ø 2.17–2.27 m

    Carries water along the hillside at a gentle gradient, keeping it high until the drop to the powerhouse.

    Construction65%
    Latest update
  3. 3

    Surge Tank

    Circular · 19.5 m × 32 m

    Absorbs pressure surges when the turbines start, stop or change load, protecting the pipe and penstock.

    Construction60%
    Latest update
  4. 4

    Penstock

    2,500 m · Ø 1.8 m steel

    Drops the water steeply towards the powerhouse, building up the pressure that drives the turbines.

    Construction49%
    Latest update
  5. 5

    Powerhouse

    3 × 34.1 MW · 940 m gross head

    A 115 m × 20 m surface powerhouse where three generating units convert the water’s energy into electricity.

    Construction90%
    Latest update
  6. 6

    Tailrace

    RCC culvert

    Returns the water to the river below the powerhouse.

    Construction100%
    Latest update
  7. 7

    Transmission Line

    1 km · 132 kV double circuit

    Connects the switchyard to the national grid.

    Construction20%
71%

As of June 2026

Overall Project Progress: 71% complete

See Construction Progress

Salient Features

Technical Specifications

Hydrology

Catchment Area
152 km²
Design Flow
12.60 m³/s
Design 100-yr Flood
166.94 m³/s
Design 200-yr Flood
184.77 m³/s
Probability of Exceedance
58.71%

Headworks

Weir Type
Raised Weir
Weir Size (L × H)
50m × 37m
Weir Crest Elevation
2,005 m above MSL
Weir Crest Length
70 m
Intake
Side Intake, 2 Orifices (2.5m × 2.5m each)

Waterways

Headrace Pipe Length
6,911.53 m
Headrace Pipe Diameter
Ø 2.17–2.27 m
Surge Tank
Circular, 19.5m dia × 32m height
Penstock Length
2,500 m
Penstock Diameter / Thickness
Ø 1.8m, 10–38mm

Powerhouse & Grid

Powerhouse
Surface type, 115m × 20m
Gross / Net Head
940 m / 914 m
Installed Capacity
97.2 MW (3 × 34.1 MW)
Dry / Wet Energy
262.54 GWh / 411.76 GWh
Tailrace Culvert
RCC, 60m × 2.7m × 2.5m
Transmission Line
1 km, 132 kV Double Circuit

At a Glance

Project Facts & Partners

Key Dates

PPA Signing
12 October 2018
Civil Contract Award
7 April 2019
Generation License
15 May 2020
RCOD (Proposed)
13 February 2027

Consultant & Contractors

Consultant
GERMDC Pvt. Ltd.
Civil Contractor
Build-Tech Construction Pvt. Ltd.
Hydro-Mechanical Contractor
Manakamana Nirman Sewa
Electro-Mechanical Contractor
CWTW, Chongqing, China
Transmission Line Contractor
Prakruthi Energy Solutions Pvt. Ltd.

Finance & Land

Revised Project Cost
NPR 13,390 Million
Lenders
Sanima (Lead), NIMB (Co-lead), Kumari, Muktinath Bikash, Laxmi Sunrise, Everest, Nepal SBI, EPF
Land Acquired (to date)
~210 Ropani

Powering Nepal's Progress, Sustainably

Get in Touch With Us

We're here to answer any questions you may have about the Isuwa Khola Hydropower Project.