Logo

Project

Case Study

Our Latest Project Highlights

We are developing a 97.2 MW hydropower project to contribute a significant supply of clean, renewable energy to Nepal's national grid and support national development.

raise weir tower crane

Isuwa Khola Hydropower Project

We are developing the Isuwa Khola Hydropower Project, a critical 97.2 MW Peaking Run-of-River scheme in Nepal's Sankhuwasabha District. This project is designed to significantly boost the national energy supply, delivering 674.30 GWh of clean, renewable energy annually. Our comprehensive approach covers every phase, from detailed civil works to advanced hydro-mechanical and electro-mechanical installations, all while fostering strong community partnerships.

97.2MW

Capacity

674.3 GWh

Annual Generation

13,390 Million

Project Cost (Est.) (NPR)

2027 Feb 13

RCOD (Proposed)

Construction of tailrace

Civil Works & Infrastructure

Our civil works form the backbone of the Isuwa Khola Hydropower Project, encompassing massive construction efforts across diverse terrains. Key structures like the raised weir, headrace pipe, surge tank, and powerhouse are being meticulously engineered and built to ensure long-term stability and operational efficiency. We prioritize robust construction practices and effective resource management.

59 % Complete

Weir & Intake Progress

4KM

Headrace Pipe Laid

73 % Complete

Powerhouse Progress

100 % Complete

Tailrace Progress

HEADRACE PIPE

Hydro-Mechanical & Electro-Mechanical Integration

The integration of hydro-mechanical and electro-mechanical systems is crucial for energy generation. Our teams are diligently working on the fabrication and installation of critical components such as penstock pipes, radial gates, and turbine accessories. We are committed to deploying cutting-edge technology to ensure the efficient conversion of water power into electricity.

47 % Complete

Hydro-Mechanical Progress

61 % Complete

Electro-Mechanical Progress

102 m

Penstock Pipe Laid (inside casing)

65 %

Equipment Delivered:

CONTRACT
2019

Signing of the

Power Purchase Agreement (PPA)

Investment
020

Achieved Financial Closure

Marking a critical step towards project funding.

tourbine
022

Awarded Package

Chongqing Water and Turbine Work Co. Pvt. Ltd. (CWTW), China.

hydro
024

Original Commercial Operation Date

Original Commercial Operation Date (COD) as per PPA.(2024)

power house
025

Construction progress

June 2025: Overall construction progress reaches 65%.

headwork
027

RCOD

February 13, 2027 (Proposed): Revised Commercial Operation Date