About Us

K.B.N.R Isuwa Power Limited is developing the 97.2 MW Isuwa Khola Hydropower Project in Sankhuwasabha, Nepal, committed to clean energy generation and sustainable development.

Who We Are

Building a 97.2 MW Peaking Hydropower Plant in the High Himalaya.

K.B.N.R Isuwa Power Limited is developing the Isuwa Khola Hydropower Project in Makalu Rural Municipality, Sankhuwasabha. Water from the Isuwa Khola, a tributary of the Arun, falls 940 metres from our raised weir to a three-unit powerhouse, generating 674.30 GWh of clean electricity every year for Nepal's national grid.

  • Clean, renewable energy
  • Peak-hour power for the national grid
  • Growing with local communities
Kalyan Bikram NeopaneManaging Director, KBNR

Why Choose K.B.N.R Isuwa Power?

Pioneering Sustainable Energy

As a leader in Nepal's hydropower sector, we are committed to delivering 674.30 GWh of clean, renewable energy annually, contributing significantly to a greener future and avoiding over 50,000+ tons of CO₂ annually.

  • Sustainable Energy Generation

    The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River scheme designed to deliver 674.30 GWh of clean, renewable energy annually to Nepal's national grid, supporting the nation's sustainable development goals.

  • Community Partnership & Development

    We actively engage with and support local communities through various social initiatives, including road construction, gabion works, and assistance for essential services like drinking water and community facilities, ensuring shared growth and prosperity.

  • 1,000+Local Jobs Created
  • 50,000+Tons of CO₂ Avoided Annually

Related Group

BIG GROUP

Founded by Group Chairman Birendra Bahadur Neopane in 1985, BIG GROUP grew from road and building construction into hydropower in 2007, and today spans clean energy, manufacturing, healthcare, hospitality, construction and technology.

Its hydropower work includes the completed Mai Khola (4.5 MW), Mai Small Cascade (8 MW) and Upper Puwa Khola (3 MW) plants and the 166 MW Super Tamor project in development.

Visit BIG GROUP
1985
Group founded
450MW
Hydropower capacity across the Group
25
Projects delivered or under way
30
Group companies

Our Journey

Milestones So Far

  1. 2019

    Civil Works Contract Awarded

    April 7, 2019

    Package 1 (Civil Works Construction) awarded to Build-Tech Construction Pvt. Ltd.

  2. 2019

    Power Purchase Agreement Signed

    October 14, 2019

    Signing of the Power Purchase Agreement (PPA).

  3. 2020

    Financial Closure

    April 10, 2020

    Achieved Financial Closure, marking a critical step towards project funding.

  4. 2020

    Generation License Issued

    May 15, 2020

    Generation license granted for the Isuwa Khola Hydropower Project.

  5. 2022

    Hydro-Mechanical Contract Awarded

    April 17, 2022

    Package 2 (Hydro-mechanical and Penstock) awarded to Manakamana Nirman Sewa.

  6. 2022

    Electro-Mechanical Contract Awarded

    2022

    Electro-mechanical package awarded to Chongqing Water and Turbine Work Co. Pvt. Ltd. (CWTW), China.

  7. 2024

    Original Commercial Operation Date

    October 13, 2024

    Original Commercial Operation Date (COD) as per PPA.

  8. 2025

    Construction Reaches 65%

    June 2025

    Overall construction progress reaches 65%.

  9. 2026

    Civil Works Reach 74%

    June 2026

    Overall civil works progress reaches 74%, with hydro-mechanical and electro-mechanical works both at 65% and the access road fully complete.

  10. 2027

    Revised Commercial Operation Date

    February 13, 2027 (Proposed)

    Revised Commercial Operation Date (RCOD).

Team Members

Meet Our Dedicated Team of Hydropower Experts

  • Mr. Birendra Bahadur Neopane

    Mr. Birendra Bahadur Neopane

    Chairman

  • Mr. Kalyan Bikram Neopane

    Mr. Kalyan Bikram Neopane

    Managing Director

  • Mrs. Ruma Rajbhandari

    Mrs. Ruma Rajbhandari

    Director

  • Mr. Ananta Karki

    Mr. Ananta Karki

    Chief Executive Officer

  • Mr. Sudhir Lamichhane

    Mr. Sudhir Lamichhane

    CFO

  • Mr. Bed Prakash Bista

    Mr. Bed Prakash Bista

    Admin & Finance Manager

  • Mr. Prasun Tumbahangphe

    Mr. Prasun Tumbahangphe

    Executive Engineer

  • Mr. Dipak Thapa

    Mr. Dipak Thapa

    Chief Engineer

  • Mr. Nibesh Thapa Magar

    Mr. Nibesh Thapa Magar

    Procurement Manager

Testimonials

What Our Partners & Communities Say

Voices from Our Partners & Communities

The Isuwa Khola Hydropower Project has brought significant improvements to our daily lives, particularly with the road development and access to essential services. It's more than just a power project; it's a partner in our community's growth.

Ramhari KhatriShare holder

Powering Nepal's Progress, Sustainably

Get in Touch With Us

We're here to answer any questions you may have about the Isuwa Khola Hydropower Project.