Overall & Component-wise Construction Progress

Overall Project Progress
71%
Overall Civil Works
74%
Raised Weir and Intake
69%
Desander
7%
Headrace Pipe
65%
Surge Tank
60%
Penstock Pipe Alignment
49%
Powerhouse
90%
Tailrace
100%
Switchyard
60%
Protection Works Along Alignment
90%
Hydro-Mechanical Works
65%
Access Road
100%
Electro-Mechanical Works
65%
Transmission Line Works
20%
Project Overview

Salient Features

Catchment Area
152 km²
Design Flow
12.60 m³/s
Design 100-yr Flood
166.94 m³/s
Design 200-yr Flood
184.77 m³/s
Probability of Exceedance
58.71%
Weir Type
Raised Weir
Weir Size (L × H)
50m × 37m
Weir Crest Elevation
2,005 m above MSL
Weir Crest Length
70 m
Intake
Side Intake, 2 Orifices (2.5m × 2.5m each)
Headrace Pipe Length
6,911.53 m
Headrace Pipe Diameter
Ø 2.17–2.27 m
Surge Tank
Circular, 19.5m dia × 32m height
Penstock Length
2,500 m
Penstock Diameter / Thickness
Ø 1.8m, 10–38mm
Powerhouse
Surface type, 115m × 20m
Gross / Net Head
940 m / 914 m
Installed Capacity
97.2 MW (3 × 34.1 MW)
Dry / Wet Energy
262.54 GWh / 411.76 GWh
Tailrace Culvert
RCC, 60m × 2.7m × 2.5m
Transmission Line
1 km, 132 kV Double Circuit

Key Project Data

Civil Contract Award
7 April 2019
PPA Signing
12 October 2018
Generation License
15 May 2020
Revised Project Cost
NPR 13,390 Million
RCOD (Proposed)
13 February 2027
Land Acquired (to date)
~210 Ropani
Consultant
GERMDC Pvt. Ltd.
Civil Contractor
Build-Tech Construction Pvt. Ltd.
Hydro-Mechanical Contractor
Manakamana Nirman Sewa
Electro-Mechanical Contractor
CWTW, Chongqing, China
Transmission Line Contractor
Prakruthi Energy Solutions Pvt. Ltd.
Lenders
Sanima (Lead), NIMB (Co-lead), Kumari, Muktinath Bikash, Laxmi Sunrise, Everest, Nepal SBI, EPF
CONTRACT
2019

Signing of the

Power Purchase Agreement (PPA)

Investment
020

Achieved Financial Closure

Marking a critical step towards project funding.

tourbine
022

Awarded Package

Chongqing Water and Turbine Work Co. Pvt. Ltd. (CWTW), China.

hydro
024

Original Commercial Operation Date

Original Commercial Operation Date (COD) as per PPA.(2024)

power house
025

Construction progress

June 2025: Overall construction progress reaches 65%.

power house
026

Construction Progress

June 2026: Overall civil works progress reaches 74%, with hydro-mechanical and electro-mechanical works both at 65% and access road fully complete.

headwork
027

RCOD

February 13, 2027 (Proposed): Revised Commercial Operation Date