Logo

Services

PROGRESS UPDATE

Hydropower in Action

headwork icon
headwork_small

HEADWORKS

The progress in the raised weir area and undersluice is on progress. The project continues to progress steadily across all major components. The elevation gains at the weir, completion of foundational elements at the undersluice, and ongoing earthworks in the pondage area indicate a positive trend toward achieving project milestones.

Raised Weir and Intake 1
Raised Weir and Intake_small size 1

Raised Weir and Intake

During the reporting period, notable progress was achieved at the undersluice. Raft concreting has been completed, with rebar works advancing up to 6 meters. Vertical and radial gate embedments are installed, and the left and right walls—measuring 4 meters and 3 meters from the bucket portion—are completed. Backfilling will proceed as the wall height increases, with adjacent rocks being either removed or grouted based on site conditions.

UNDERSLUICE
Undersluice_small

Undersluice

During the reporting period, notable progress was achieved at the undersluice. Raft concreting has been completed, with rebar works advancing up to 6 meters. Vertical and radial gate embedments are installed, and the left and right walls—measuring 4 meters and 3 meters from the bucket portion—are completed. Backfilling will proceed as the wall height increases, with adjacent rocks being either removed or grouted based on site conditions.

PONDAGE AREA
Pondage Area_small

Pondage Area

In the pondage area, slope cutting and heavy excavation are ongoing along the right bank upstream of the raised weir, spanning approximately 150 meters in length with a slanted height of 27 meters. A structural solution is proposed for this section, involving the construction of an inclined wall with a horizontal beam and boulder packing from an elevation of 2000 meters down to the riverbed. The remaining area is shaped into a gentle slope of 1:3 or 1:4 toward the riverbed.

HEADRACE PIPE
HEADRACE PIPE aligh small

HEADRACE PIPE

Headrace pipe (HRP) works are progressing steadily. The alignment is accessible by motorable road, aiding transport and construction. Excavation is ongoing at crossing points, with blasting completed. Pipe laying, concreting of anchor blocks, and support pier works are active along the route. 40 anchor blocks are completed, jacketing is underway, and 4 km of pipe is already laid. Four major crossings for siphons and bridges are under excavation, with designs in progress based on completed topo surveys.

surge tank icon
surge tank small

Surge Tank

Concreting work up to 6 meters from the crank level (EL.1990.6) has been completed. However, the work is currently on hold, with plans to use pumps from the powerhouse for future concreting activities. The backfilling around the surge tank is already completed. Work Progress: 60% Complete, 40% Remaining.

PENSTOCK PIPE
penstock pipe small

Penstock Pipe

Excavation from Anchor Block 17 to the concrete casing area upstream of the powerhouse has been completed. A saddle pad is installed in the excavated section to support the penstock pipe. Concrete casing works for the inclined penstock are ongoing upstream of the powerhouse, indicating active construction in that area. Site clearance and preparatory activities for the laying of the penstock pipe are in progress along parts of the penstock alignment. Additionally, bioengineering is proposed for the inclined penstock section to stabilize the soil and prevent erosion.

power house icon
POWERHOUSE small

POWERHOUSE

Civil works at the powerhouse have reached up to the corbel beam level, with rebar installation currently underway. The machine floor slab is partially left open as per the EM contractor’s specifications for embedding turbine and generator components. The turbine casing is expected to arrive soon for later installation. Additionally, the cooling chamber is almost complete, pending only the top slab.

tailrace 1
POWERHOUSE small

Tailrace

The tailrace of length 82 meters including the cooling pond has been completed.

Lets Talk to Us

Get Free Counselling

    Testimonials

    What our clients say about Our Hydropower ?

    Voices from Our Partners & Communities

    "The Isuwa Khola Hydropower Project has brought significant improvements to our daily lives, particularly with the road development and access to essential services. It's more than just a power project; it's a partner in our community's growth."

    testi_1_1

    Ramhari Khatri

    Share holder

    Community Impact

    "The Isuwa Khola Hydropower Project has brought tangible benefits to our village. The new access roads have significantly improved connectivity, and their support for our local Gumba and drinking water schemes shows a true commitment to community well-being. This project is making a real difference in our lives."

    testi_1_2

    Mr. Karma Sherpa

    Community Leader, Makalu Rural Municipality

    Engineering & Progress

    "As a partner involved in the civil works, I've been consistently impressed by the scale and precision of the Isuwa Khola Hydropower Project. The progress on critical structures like the powerhouse and headrace pipe is remarkable, reflecting strong engineering and dedicated execution. It's a privilege to contribute to such a vital national asset."

    testi_1_3

    Mr. Ramesh Pokharel

    Construction Manager, Civil Works Contractor

    Strategic Partnership

    "Our collaboration with K.B.N.R Isuwa Power Limited on the transmission line has been a testament to effective partnership. The project's strategic importance for Nepal's energy future is clear, and we're proud to be part of an initiative that is so crucial for national development and energy independence."

    woman

    Ms. Anjali Singh

    Project Coordinator, Transmission Line Partner

    Shape Image